Basic and detailed design for additional installation of waste incineration facility in Jangsu-gun

  • 발주처

    Jangsugun

  • 사업기간

    2020.05-2022.06

  • 사업규격

    - Incineration: 11.5 tons/day
    - Land area: 9,536㎡
  • 프로젝트
    이미지

  • 사업설명

    In Jangsu-gun, due to the increase in waste generation every year, the amount brought into domestic waste treatment facilities (landfill, incineration facility) increases, and the flammable waste treatment and storage problems excavated in the recycling landfill facility creation and maintenance project that has been promoted since 2017 are solved. Additional installation of incineration facilities to